Goodyear Recreation Campus Is Getting Its Second Half. Here's What's Settled and What Isn't.

On a Saturday when every field at the Goodyear Recreation Campus is booked and the lazy river is full, where does the next car park? That question, along with where the irrigation water comes from, is what the City Council is working through on the campus expansion. The splash pad, the dog park and the skate plaza are already decided. Water and parking are the parts still being designed, and they will decide how the city's first regional park works for the people who use it most.

The money and the amenity list are already locked

The city adopted its FY2027 budget on June 8, 2026, and it funds design and construction of the remaining 46 acres of the campus at 420 S. Estrella Parkway. The October 19 council work session packet describes the result as "the first regional park in Goodyear."

The city's adopted FY2027–2031 capital improvement plan lists "Goodyear Recreation Campus: Expansion Phase 2" at $68,331,500 in total. That money is spread across three fiscal years, and most of it is set for FY2029, the year construction is expected to finish:

Fiscal year Phase II allocation
FY2027 $8,845,000
FY2028 $10,661,500
FY2029 $48,825,000
Total $68,331,500

The amenities came from years of public input. The city's 2023 Parks and Recreation Master Plan drew nearly 23,000 community inputs from more than 40 stakeholder meetings, eight public meetings, six community events and a survey. Finishing Phase II came out as one of the plan's top priorities. The staff report lists what Phase II will include:

  • Additional ballfields, including an adaptive field
  • Additional pickleball courts
  • An expanded multi-use turf area
  • A splash pad
  • A dog park
  • A skate plaza
  • Public art
  • Connected pedestrian pathways

Every item on that list adds visitors. That's why the unresolved questions are about supporting systems rather than features.

Water: a pond that is also a design question

The full campus will be 86 acres once Phase II is built, and staff estimate it will need about 66 million gallons of irrigation water a year. Phase I currently waters its grass with potable water. Staff recommend switching the whole campus to non-potable water from the Roosevelt Irrigation District.

That switch requires storage. The site would need about 2.9 acre-feet of water on hand, enough for five days of operation. Staff propose an irrigation pond that would double as a feature visitors can see and use. The pond and related irrigation infrastructure are estimated at $1.5 million to $2.3 million. Moving to RID water is projected to cut operating costs by about $415,800 a year. The proposed location sits outside the 10,000-foot radius that Phoenix Goodyear Airport land-use restrictions set.

At those figures, the annual savings would cover the high-end pond estimate in under six years. Parks Superintendent Jeremy Figueroa made the case for the pond at the work session, as reported by the West Valley View:

"This option is one that can give back to the community by doubling as a public amenity and eliminating the use of potable water for irrigation."

Council members raised concerns about open water near children and recreation facilities, the West Valley View reported. Councilmember Vicki Gillis suggested looking at fencing or other safety measures. "Even if it doesn't have to be a huge fence but something that would go around it," she said. The pond, then, is a staff recommendation still being refined. It has not been adopted.

Parking: the Estrella Parkway problem

Staff estimate Phase II will need about 555 more parking spaces. They weighed two ways to get them:

  1. A parking structure. About 271 spaces at an estimated $8 million to $13 million.
  2. Expanded surface parking. About 705 spaces at an estimated $3.5 million to $7 million.

A garage would leave the campus well short of the estimated need at a higher price, while the surface option clears it by about 150 spaces. Staff recommended surface parking and said shade structures could be added later.

The West Valley View reported that Vice Mayor Brannon Hampton backed the surface recommendation and Gillis encouraged more study of a structure. Mayor Joe Pizzillo focused on what happens on big event days if parking runs short and visitors start crossing Estrella Parkway on foot. "I'm more concerned about people getting hit by cars because there's not enough parking spaces," Pizzillo said.

This is the decision people will feel most directly. The campus already holds two lighted baseball and softball fields, two lighted multipurpose fields and an aquatic center with water slides, and Phase II adds more fields, more courts and a splash pad. How many cars fit on site will determine whether a tournament Saturday stays inside the campus or spills onto the parkway.

The community room has no funding yet

The third open question is a community room of about 6,200 square feet, with capacity for roughly 287 people. It would add to the existing 3,000-square-foot multipurpose room built in Phase I and roughly double the campus's meeting space. The West Valley View put its estimated cost at $9 million to $11 million and reported that it is not in the current project budget.

The October 19 session was for discussion and direction only, and no action was taken. Staff plan to return with more information and alternatives on all three items as design continues.

When each piece is expected

The staff presentation sets out a forecast timeline. All of these dates are projections:

  • October 2026: Council review of the 30% design. The council's direction on water, parking and the community room feeds into that design package.
  • November/December 2026: Selection of a construction manager at risk.
  • April 2027: 60% design development milestone.
  • April–May 2027: 60% design presented to the Parks & Recreation Advisory Commission.
  • Winter 2028: Construction.
  • FY2029: Ribbon cutting.

Design itself runs from February 2026 through February 2028. That leaves more than a year between now and the first construction crews, and the next public look at the plan comes at the commission presentation next spring.

What Phase I offers this season

All of that planning builds on a campus that opened to the public on July 3, 2021. The 48,000-square-foot Goodyear Recreation Center has a multipurpose gym, fitness and weight areas, an elevated indoor walking and running track, a teen activity and eGaming room, and the 3,000-square-foot multipurpose room.

The aquatic center has an eight-lane competition pool with diving boards, a zero-depth-entry play pool, a leisure pool, a lazy river and two 27-foot water slides. The fall and winter lap-swim schedule runs from September 28 into February 2027:

  • Monday through Friday, 6 to 8 a.m. and 5 to 7 p.m.
  • Saturday and Sunday, noon to 2 p.m.

The 30-acre park has lighted tennis, basketball, pickleball and sand volleyball courts alongside its lighted fields. It also has group ramadas, public art and a one-mile walking loop. The playground includes a zipline, a circular swing for younger children, musical elements and sensory panels. The city's November recreation calendar includes open pickleball, fitness and yoga classes, teen drop-in, youth soccer, senior activities and a clay-figurine class running into December.

The next big gathering on the campus is Saturday, November 14. The city's Chalk Art in the Park runs from 9 a.m. to 2 p.m. at the Goodyear Recreation Center, with public chalk art, tie-dye, a DJ and food trucks. It's a free look at how the existing lots handle a crowd, which is the question the Phase II parking plan has to answer at a larger scale.

Two other cool-season options sit close by. The Select Sundays Farmers Market at Goodyear Ballpark, 15461 W. Festival Way, runs November 15 and December 13 from 8 a.m. to 1 p.m. At Estrella Mountain Regional Park, 14805 W. Vineyard Ave., the Maricopa County Parks calendar lists these November programs:

  • November 14, 7 a.m.: Bird walk with Tom Locascio
  • November 15: Morning fitness hike, 20 spots
  • November 17: Desert 101 hike, 20 spots
  • November 20: Guided plant hike and the "All About Saguaros" Discovery Station
  • November 28: Tired Turkey Wildlife Watch

Civic projects like the Recreation Campus expansion shape how a part of Goodyear feels day to day, and that matters when you want a clear read on what your own home is worth. David Ayers keeps track of Goodyear's projects and its MLS data so you can see both. Get your instant home valuation.