Arnies closed on Sept. 21 after 45 years at 300 Admiral Way. The boutique hotel planned for that site has carried an estimated construction start of 2029. Meanwhile, the north end of the Edmonds marina is already changing. The Landing building has a row of small businesses in it. In June, the Port of Edmonds Commission authorized a contract to tear down the Port's old cinder-block office a few doors south. Between now and mid-December, the marina has a cleanup dive, the Christmas Ship and the Port's own holiday night.
How Arnies ended
The restaurant closed with a sign on the door. It read, in part, "After 45 years of service, Arnies Restaurant will close effective September 21, 2026. Unfortunately, the current business climate does not allow us to continue." My Edmonds News reported the closure the next day. The paper added that management wasn't available to comment. It also reported a customer's account that the restaurant had planned to stay open until construction began on the new hotel.
That plan dates back to June 2025. The Port of Edmonds owns the land under the Landing. It signed a 50-year ground lease, effective June 6, 2025, with Mike and Ryan Appleby, a local father-and-son team doing business as 1010 Development. The Applebys bought the building from Catspaw LLC. Catspaw's managing member, Peter Challman, had told the Port in early 2024 that the company would not extend its lease past the end of 2029. "We have roots dating back five generations in Edmonds," Ryan Appleby said in the Port's announcement. Acting Executive Director Brandon Baker explained why the Port's review took so long: "There is only so much commercial waterfront property in Edmonds."
That 2025 coverage described a boutique hotel on the building's current footprint. Plans called for a full-service restaurant, sauna and spa, a social club, event space and a ground-floor café. My Edmonds News reported that the project would be a complete teardown, with construction estimated to start sometime in 2029. At the time, the Port called the design preliminary and said it would need extensive permitting, including design review with chances for public input. No room count, building height or rendering has been made public. Arnies has now closed years ahead of that 2029 estimate. That leaves the Landing with an empty anchor space and a long runway before any construction starts.
The Landing keeps its doors open
A letter to the editor in The Beacon's Oct. 1 issue argued that the building "is far from quiet." It named the businesses moving in around the dark restaurant. Here's who is there, by suite, based on each business's own listing:
- Aloha Northwest, Suite 101. A Hawaiian-inspired boutique and gift shop that lists Tuesday through Saturday hours.
- Snoqualmie Ice Cream, Suite 102. My Edmonds News reported its opening in March 2026, with hours of 11 a.m. to 7 p.m. daily. The October letter still names the shop. Hours that were set in March may have shifted for fall, so check before you walk over.
- Mane Salon, Unit 106. Run by Vanessa Weinbach, with online booking and Tuesday through Saturday hours.
- CoSA, Chapel of Sound & Art, Suite 107. A gathering space, gallery and retail shop envisioned by Edmonds resident Rev. Dr. Naomi Fay, open by appointment and for scheduled gatherings.
- Vibe High Sound Lounge, Suite 108. Shares space with CoSA and books sessions Friday through Monday by appointment.
- Sirius Healing, upstairs. Teri Burnett's studio.
- Gifts of Grief Gallery, run by Megan Dillon. Its own site says doors open on Oct. 31, 1 to 6:30 p.m., under the name Edmonds Wellness Collective at The Landing.
That last date falls this Saturday. The opening adds one more lit window to a building that lost its biggest tenant in September.
The new tenants have something in common. Most are small, run by their owners, and work by appointment or on limited days. For a building with a ground lease running decades and a teardown expected at some point, that fits. A 45-year restaurant needed a full kitchen, staff and a long horizon. A gallery or salon can move in, build a following and plan around a hotel timeline that is still preliminary. Nothing has been reported yet about a new tenant for the Arnies space itself.
Next door, the change has a contractor and a date
The Landing's future is still a design concept. The parcel a few doors south is much further along. The Port's old administration and maintenance building at 336 Admiral Way is the next piece of the North Portwalk and Seawall Reconstruction project. The Port plans to take it down so "the prime waterfront parcel can be the site of a beautiful new public plaza." The offices are already out. The Port moved its administration and maintenance operations to 471 Admiral Way, in a new building finished in early 2024.
Here is where the timeline stands, from the Port's own records:
- June 8, 2026. The Port Commission voted unanimously to let staff sign a construction contract with Trico Companies LLC for Phase Two. Commissioners asked about the contractor's experience with marine work on tight sites. Staff noted that Trico has worked for the Port before.
- End of 2026. The Port estimates demolition, site preparation and electrification work will start then. Phase Two is budgeted at $3.2 million. A $1.5 million WSDOT port electrification grant and a $500,000 RCO ALEA grant cover part of that, and Port reserves cover the rest.
- May 1, 2027. The state bid notice sets this as the target for substantial completion.
- 2027/2028. Phase Three is estimated to start. It rebuilds the marina seawall that holds up the wood-plank Portwalk and replaces the decking with a nonslip concrete and glass-block surface that lets light reach the water below. It also adds railings, lighting, native plantings and the plaza itself, with raised seating, a performance space, art installations and public restrooms. The estimate is $32.4 million, and the Port is still seeking grants and partner funding.
The Port marks both the timeline and the costs as subject to change.
The first big physical change at the north end of the marina comes from the Port, not from the hotel. This winter's demolition at 336 Admiral Way clears space for a public plaza first. Only after that does the Landing's private redevelopment start, on its own later schedule. If you walk the Portwalk from the Edmonds Public Fishing Pier toward Marina Beach Park, expect a construction zone near the Port's end of the boardwalk this winter.
Where the waterfront still feeds you this season
With Arnies gone, the dinner-with-a-marina-view list along Admiral Way is shorter. It still has options at most price points and hours:
Anthony's HomePort, 456 Admiral Way, serves dinner from 4 to 8:30 p.m. Monday through Thursday and 4 to 9 p.m. Friday and Saturday. On Sundays it opens at 10 a.m. and closes at 8:30 p.m.
Anthony's Beach Café shares the 456 Admiral Way address. It's open daily from 11:30 a.m. to 8:30 p.m., seats walk-ins only, and covers the lunch hours HomePort doesn't.
CommonGrounds at the Edmonds Waterfront Center serves coffee, ice cream, pastries and lunch. Hours are 8 a.m. to 4 p.m. on weekdays and 9 a.m. to 4 p.m. on weekends. The center notes that it is a rental venue on weekends, so a private event can affect Saturday plans.
Epulo Bistro, 190 Sunset Ave., Suite B, opens daily from 4 to 9 p.m.
Salish Sea Boathouse Taproom in Harbor Square, 180 W. Dayton St., is closed Monday and Tuesday. It opens 3 to 10 p.m. Wednesday and Thursday, noon to 10 p.m. Friday and Saturday, and noon to 9 p.m. Sunday. It also lists closures on Thanksgiving, Christmas Eve, Christmas Day and New Year's Eve.
The marina calendar through December
The Port and its partners already have the rest of the year on the books. Several events use the same docks that Phase Two construction will soon border:
- Sunday, Nov. 8, 9 a.m. to noon. Annie Crawley's Scuba Diving Team returns for its twice-yearly underwater cleanup at the marina, 458 Admiral Way. Divers have to be pre-approved, but anyone can help on shore hauling debris. The Port suggests warm clothes, gloves and a bucket.
- Saturdays from Nov. 7. The Edmonds Museum Holiday Market runs 9 a.m. to 2 p.m. on Nov. 7, 14 and 21 and Dec. 5, 12 and 19, on 5th Avenue North and Bell Street outside the museum at 118 5th Ave. N. It's a short walk uphill from the ferry.
- Saturday, Nov. 28, 3 to 5 p.m. The Edmonds Chamber's tree lighting is at Centennial Plaza, with the countdown at 4:30 p.m.
- Sunday, Dec. 6. Argosy's Christmas Ship schedule has it leaving the Port of Edmonds, with a shoreline performance at the Edmonds Fishing Pier from 4:10 to 4:30 p.m.
- Thursday, Dec. 10. The Port's annual Holiday Night at the Marina returns to 458 Admiral Way, with music, food trucks, free hot drinks and treats, and decorated boats.
Dec. 10 may be the last big public gathering on the north docks before the end-of-2026 demolition window opens. A year from now, the cinder-block building at 336 Admiral Way should be gone and the site prepared for a plaza. The Landing will be one more year into its lease, and its next tenant lineup is still being written one suite at a time.
If you own a home near the Edmonds waterfront and want to know how this winter's changes on Admiral Way fit into your home's value, David Ayers can walk you through local sales and give you a clear, data-driven picture of where your home stands. Get your instant home valuation, and when you're ready, we'll talk through what it means for your plans.